Tentative Schedule

as of March 14, 2018


EVENT:                                                    ANTICIPATED DATE:

Public Stakeholders Meeting                                   March 26, 2014


Public Information Meeting                                      November 6, 2014


NEPA & Plans Public Hearing                                  February 25, 2016


Anticipated Project Funding Complete                    February 2017


RFP Advertised                                                       July 2017


Design-Build Contractor Hired                                February 2018


Public Information Meeting                                     April 2018


Start of Site Preparation                                         May 2018


Trail Detours Begin                                                 May 2018


Plans, Permits Complete by Contractor                  June 2018


VDOT Approval of Plans                                        June 2018


Street Detours Begin                                              August 2018


Start of Demolition                                                  August 2018


Start of Construction                                              September 2018


Street Re-Opened to Vehicles                               March 2019


Trail Re-Opened                                                    April 2019


Completion of Construction                                   June 2019


Dedication of New Bridge                                      July 2019


Project Closeout                                                    July - Sept. 2019



*Project Schedule is highly dependent upon timely authorizations by VDOT and FHWA, and the weather.





Copyright 2018. Town of Luray.  All Rights Reserved.                                                                                        Website Design by: Shannon Sankar/Standout Arts, LLC