Tentative Schedule

as of March 14, 2018

 

EVENT:                                                    ANTICIPATED DATE:

Public Stakeholders Meeting                                   March 26, 2014

 

Public Information Meeting                                      November 6, 2014

 

NEPA & Plans Public Hearing                                  February 25, 2016

 

Anticipated Project Funding Complete                    February 2017

 

RFP Advertised                                                       July 2017

 

Design-Build Contractor Hired                                February 2018

 

Public Information Meeting                                     April 2018

 

Start of Site Preparation                                         May 2018

 

Trail Detours Begin                                                 May 2018

 

Plans, Permits Complete by Contractor                  June 2018

 

VDOT Approval of Plans                                        June 2018

 

Street Detours Begin                                              August 2018

 

Start of Demolition                                                  August 2018

 

Start of Construction                                              September 2018

 

Street Re-Opened to Vehicles                               March 2019

 

Trail Re-Opened                                                    April 2019

 

Completion of Construction                                   June 2019

 

Dedication of New Bridge                                      July 2019

 

Project Closeout                                                    July - Sept. 2019

 

 

*Project Schedule is highly dependent upon timely authorizations by VDOT and FHWA, and the weather.

 

 

 

 